MONROVIA, Liberia — Former Public Works Minister Ruth Coker Collins has provided a detailed account of the controversial Bopolu City Chip-Seal Road Project, disputing allegations of financial impropriety and maintaining that the government retained more than US$340,000 after disagreements with the contractor stalled the remaining construction work.
Appearing on OK FM 99.5, Collins addressed questions about the US$900,000 contract awarded to YSM Incorporated, explaining the project’s history, payment arrangements, construction delays, and eventual termination.
She said the agreement was signed on November 14, 2019, to rehabilitate about 2.9 kilometers of urban roads across three locations in Bopolu City, Gbarpolu County.
According to Collins, the project was designed to improve road conditions, reduce dust pollution, and limit the recurring expenditure associated with maintaining unpaved city streets.
She explained that chip-seal pavement is a lower-cost road treatment compared with conventional asphalt and is generally applied to roads that do not experience heavy traffic.
Collins stressed that she assumed office at the Ministry of Public Works in 2022, several years after the contract had been awarded, adding that the agreement had already passed through the required procurement and approval processes.
On the financial arrangements, she said YSM Incorporated received US$315,000, representing 35 percent of the contract value, as an advance payment intended to support mobilization and the commencement of construction.
She attributed the subsequent interruption of work to the COVID-19 pandemic, which resulted in a government-ordered suspension of construction activities for approximately nine months. The prolonged stoppage, she explained, exposed portions of the prepared road sections to deterioration during the rainy season.
Following the resumption of activities, Collins said the contractor completed additional work, bringing the documented physical progress to 60 percent.
She used a completion certificate dated September 14, 2020, to explain a payment of US$126,710.53, representing an additional 15 percent of the contract price.
According to her explanation, the 60 percent completion figure reflected the cumulative progress recognized under the contract, while the 15 percent represented the specific payment being processed.
Collins disclosed that total payments to YSM Incorporated during the period under review amounted to US$559,947.95.
She maintained that the payments corresponded with work undertaken and were processed through the ministry’s engineering and administrative approval channels.
However, the remaining construction phase became contentious when the ministry sought to move forward with the chip-seal application.
The former minister said officials discovered that YSM Incorporated lacked the equipment required for that stage of the project and was advised to subcontract the work.
She explained that the contractor subsequently presented a revised cost that substantially exceeded the amount remaining under the original agreement.
Collins said the ministry rejected the proposed increase, insisting that the outstanding work be completed within the remaining contractual balance of approximately US$340,052.
Several meetings were reportedly held to resolve the disagreement, including discussions involving lawmakers connected to the Legislature’s public works committee. However, the parties failed to reach an agreement before the ministry terminated the contract.
She insisted that the outstanding funds were never paid to the contractor and remained with the government.
Addressing the corruption allegations, Collins disclosed that she had appeared before the Liberia Anti-Corruption Commission (LACC) two or three times to provide information concerning the project.
She said she had not been informed of any findings establishing wrongdoing on her part and questioned why accusations continued circulating without the publication of the Commission’s conclusions.
Collins also raised concerns about the circulation of internal government documents, while arguing that public discussions about the project should be grounded in the actual contract, payment records and engineering reports.
She challenged critics to examine the available documentation and consider the circumstances surrounding the project’s suspension, rather than draw conclusions from isolated figures in the records.
The interview has renewed attention on the Bopolu road contract, particularly the US$559,947.95 reportedly disbursed, the unfinished chip-seal component and the circumstances surrounding the termination of YSM Incorporated’s agreement.