MONROVIA, Liberia — Former Public Works Minister Ruth Coker Collins has challenged allegations surrounding the delayed Bopolu City Chipseal Road Project, arguing that any assessment of the controversy must begin with the original contract, subsequent implementation challenges and official records documenting the project’s history.

In a public statement, Collins maintained that she inherited the project after its initial award and encountered significant difficulties that had already affected implementation. She said her tenure at the Ministry of Public Works involved efforts to re-engage the contractor and address outstanding issues rather than decisions concerning the project’s original procurement.

The controversy involves a 2.9-kilometre urban road project in Bopolu City, Gbarpolu County, which was initially valued at US$900,000.

Collins, who previously served as Deputy Minister for Technical Services before becoming Minister of Public Works, said she supports public scrutiny but cautioned against assigning responsibility without examining the full documentary history.

Original Contract Signed in 2019

According to Collins, the Bopolu road project was awarded to YSM Incorporated on November 14, 2019, under an agreement signed between the company and the Ministry of Public Works.

The company was represented by its Chief Executive Officer, Ali Harkous, while the agreement was signed on behalf of the Ministry by the late Senator Mobutu Vlah Nyenpan, who served as Public Works Minister at the time.

The project, financed through the National Road Fund of Liberia, carried an original contract value of US$900,000 for approximately 2.9 kilometres of urban streets.

Collins said the agreement subsequently received the indicated approvals from the Ministry of Finance and Development Planning and the Ministry of Justice.

She also identified US$315,000 as the advance payment made to the contractor, representing 35 percent of the original contract value, following verification of the bank guarantee and payment records.

She stressed that she had no involvement in negotiating, awarding or signing the original agreement, noting that the contractual obligations and financial arrangements were established before her appointment as Deputy Minister for Technical Services.

COVID-19 Outbreak Complicated Implementation

Collins attributed part of the project’s prolonged delay to disruptions associated with the COVID-19 pandemic, which reportedly resulted in approximately nine months of suspended construction activities.

She said that upon assuming office, the Ministry was confronted with several infrastructure projects experiencing delays, including the Bopolu road initiative.

According to her account, the immediate challenge was to secure the contractor’s return to the construction site and establish a practical arrangement for continuing the work.

She said the Ministry subsequently engaged YSM Incorporated, held discussions and negotiated arrangements that resulted in the contractor’s remobilization.

Collins described the intervention as an effort to prevent further deterioration of the project and safeguard the government’s financial commitment.

She argued that abandoning an existing contractual arrangement without exploring possible solutions would have further delayed the delivery of infrastructure promised to Bopolu residents.

December 2022 Assessment Identified Outstanding Engineering Works

Collins also referred to a site assessment conducted in Bopolu on December 4, 2022, which documented the physical condition of the roads and the activities required before chipseal pavement could be applied.

The assessment involved the Assistant Minister for Operations and Victor McKay, identified in the document as the Ministry’s Social Worker Proxy for the Resident Engineer.

Three road sections were examined, with the report identifying outstanding preparatory and engineering requirements.

For Administrative Roads 1 and 2, covering approximately 900 metres, the assessment identified surface correction, vegetation clearance, stone pitching and culvert installation.

On King Sao Boso Street, measuring approximately 800 metres, the outstanding activities included the removal of structures within the road right-of-way, clearing of vegetation and surface regravelling.

The Fawenta-to-Eric’s Scott United Methodist Church Road also required vegetation clearance, regravelling and culvert installation before the application of chipseal.

Collins said the assessment demonstrates that the project involved several technical requirements beyond the final paving process.

She maintained that any evaluation of the contractor’s performance should consider the engineering conditions, drainage requirements and right-of-way challenges documented during the assessment.

February 2023 Report Raised Concerns Over Contractor’s Capacity

Another document cited by Collins is a project update dated February 24, 2023, titled Update on Gbarpolu Chipseal Project.

The report reportedly outlined several factors contributing to the project’s slow progress, including COVID-19 disruptions, delayed payments, inadequate equipment, limited manpower and repeated interruptions in construction activities.

It also raised concerns about the contractor’s inability to complete the assignment within the expected period.

According to Collins, the report indicated that the remaining road works required earthworks, drainage construction and chipseal application.

She further explained that in June 2021, YSM Incorporated had been instructed to subcontract the chipseal component to a company meeting the Ministry’s technical approval requirements.

However, the contractor reportedly failed to secure an agreement with a qualified company and subsequently submitted a revised budget, citing increased operational expenses, particularly higher fuel prices.

Collins said the report also documented discussions held on November 30, 2022, during which the contractor indicated that it could not remobilize without receiving additional payment.

The document further questioned whether YSM possessed the technical and mechanical capacity required to complete the outstanding works.

As a result, the Ministry reportedly began considering the possibility of engaging another contractor to undertake the remaining activities.

Collins said the proposed additional expenditure and recommendation concerning a replacement contractor were referred to the Ministry’s Procurement and Legal Teams for review.

She argued that these records establish that the implementation problems were documented and subjected to administrative consideration before her departure from the Ministry.

Collins Calls for Evidence on Public Funds

Addressing allegations of financial mismanagement and possible misuse of government resources, Collins said project delays and contractual disagreements should not automatically be interpreted as evidence of financial misconduct.

She emphasized that public funds are entrusted to government officials for the benefit of citizens and must be properly accounted for.

However, she insisted that allegations of wrongdoing should be supported by verifiable evidence rather than conclusions drawn solely from the project’s failure to meet its original implementation schedule.

Collins identified several areas requiring examination, including the original contract award, payments made to the contractor, work completed before and after the interruption, proposed variations, procurement approvals and the actual status of construction at different stages.

She said an objective review should establish whether payments corresponded with certified work, whether additional financial requests were properly justified and whether the applicable procurement and engineering procedures were followed.

The former minister also welcomed the submission of credible evidence to the appropriate accountability institutions, maintaining that every official involved in the project’s administration should be prepared to answer questions concerning decisions taken during their respective periods of service.

Bopolu Residents Deserve Answers

Collins said the political disagreements surrounding the project should not overshadow the interests of residents who have waited for improved road infrastructure.

She maintained that the people of Bopolu deserve a transparent explanation of the project’s financial history, the amount of work completed, the funds disbursed and the measures required to deliver the remaining construction activities.

She called for the examination of the original contract, the December 2022 engineering assessment, the February 2023 project update, payment records and subsequent administrative decisions.

According to her, reviewing these documents together would provide a more complete understanding of the project’s challenges and help determine where responsibility lies.

She cautioned against examining isolated portions of the project’s history while overlooking decisions made by other officials and administrations involved in its implementation.

Former Minister Reaffirms Support for Accountability

In concluding her statement, Collins acknowledged that infrastructure projects can encounter technical, financial and administrative obstacles, adding that she would not claim that every difficulty inherited during her tenure was resolved.

Nevertheless, she maintained that there is a clear distinction between inheriting a delayed government project, attempting to restore its implementation and deliberately misappropriating public resources.

She said she remains prepared to account for decisions taken during her service at the Ministry but expects any investigation to be conducted impartially and supported by documentary evidence.

Collins urged those making allegations to identify the specific decisions under question and submit relevant evidence to the appropriate institutions rather than rely on political interpretations.

She concluded that accountability should extend to everyone involved in the project’s history, regardless of official position or political affiliation.

“The people of Bopolu deserve development. The people of Liberia deserve accountability. And above all, the truth deserves to be told in its entirety,” Collins stated.

Ruth Coker Collins previously served as Deputy Minister for Technical Services and Minister of Public Works of the Republic of Liberia.

Related posts

Liberian-American A. Patrick Sowah Launches Historic Campaign for New Brighton City Council‎

Maryland Online News

River Gee Senatorial Hopeful Kunkunyon Teh Arrives in County, Announces Community Support

Maryland Online News

Nyenpan Unveils 2029 Sinoe Senate Ambition, Promises People-Centered Campaign